A free zone audit signed in seven weeks
Audit report signed seven weeks after year end, in time for the licence renewal.
Client
Free zone logistics company
Sector
Logistics
Location
UAE
Year
2025
Engagement
Annual, third year
Led by
Audit

7 weeks
Year end to signed report
11 days
Finance team time on the audit
1 month
Licence renewed early
(01) In short
A logistics company in a Dubai free zone kept renewing its licence late because its audit ran late. We moved the work into the year and signed in seven weeks.
(02) The challenge
The company's free zone licence renewal depends on audited accounts. For two years running the audit had dragged into the fourth month after year end, and the licence was renewed with days to spare.
Each year the previous auditor sent new requests in the final weeks, and the finance team of three spent most of the first quarter answering them.
(03) What we did
- Agreed the timetable and the full request list in the first month of the financial year.
- Tested controls over freight billing and payments during the year, not after it.
- Ran fieldwork remotely in the two weeks after year end, with one visit to the warehouse for the stock count.
- Ranked the findings in the management letter by their cost to the business.
(04) The outcome
The audit report was signed seven weeks after year end, and the licence was renewed a month early. The finance team spent eleven days on audit requests, down from most of a quarter.
Three findings on freight billing were fixed before the next year started, recovering revenue that had been going uninvoiced.
In their words
The audit stopped being the thing we dreaded every March.